The Hermione case enters a new phase, with the extension of its observation period decided on March 25, 2026 by the La Rochelle court.
A long-lasting receivership
Placed in receivership since September 2025, the Hermione La Fayette association has been granted a further extension. The observation period has been extended until the beginning of July 2026. This decision follows an initial extension granted in January 2026. The court considers that the project presented remains credible, but still requires guarantees.
Opening the site to the public is envisaged as a lever. Showing the boat as it is being restored would make the progress visible and maintain interest in the project, even if this is not the option that will raise the missing sum.
Financing requirements still estimated at 5 million euros
The key point remains financial. Around 5 million euros are needed to complete the refurbishment. The calendar plays a role. The year 2026 marks 250 years of American independence, an event historically linked to the Hermione. Added to this is the 400th anniversary of the French Navy.
Three takeover projects and one central question: to sail or not to sail?
The current procedure is attracting several takeover candidates. Three bids have been put forward, with different orientations.
Some projects envisage a quayside operation, centered on a museum function. Others maintain the objective of navigation.
This choice determines the whole project. A seagoing vessel implies a crew, operating costs and ongoing maintenance. On the quayside, management becomes simpler, but maritime use disappears.
A decision expected in early July 2026
The court must rule at the end of this new observation period. The deadline set for the beginning of July 2026 should enable the situation to be clarified. In the meantime, the association is continuing its efforts. The objective remains to present a structured recovery plan, capable of guaranteeing the continuation of the shipyard and the future operation of the vessel.

/ 
















